  • Client: Gardiner & Theobald
  • Location: Immingham
  • Value: £287K

Project Description

The construction of the new Oasis academy in Immingham necessitated the remodelling of the existing Pelham Road, the main thoroughfare in Immingham. The 6 week programme of works involved the provision of a raised table and roundabout, a layby, footpath works, street lighting, traffic lights and signage along with general landscaping. Works were carried out in live traffic conditions throughout the course of the contract utilising traffic management and temporary signals during site working hours.