All Projects
Recent Contracts
  • ABP Canopy Extension- JemBuild
    Shed 5 Canopy Extension, King George Dock, Hull

    The design and construct of a new 80m x 20m canopy extension to the existing shed in line with a previous extension.

    This fast track project had to be carried out with minimum disturbance to the clients tenant who operate a very busy timber distribution company within the core of this busy dock.  Continued access of the existing shed was required throughout the full duration of the works.

    The extension consisted of a twin span steel portal frame (maximising floor space for timber storage), cladded to the roof and side walls, with an open frontage. The steelwork was erected on reinforced concrete pad foundations which were constructed on precast concrete piles.

    New electrical lighting and alterations to existing electrical services was required including removal of a high mast lighting column and new lightning protection was also installed.

    A perimeter concrete dwarf wall and associated surface water drainage and external block paved and concrete reinstatement completed the project.

    The project was completed on time and on budget despite encountering major unknown underground obstructions at the foundation stage which delayed piling and foundation works.

  • Kingeo Substation - JemBuild
    Associated British Ports - Kingeo Substation

    The project consisted of the construction of a major substation to power the new Siemens wind turbine facility on Alexandra Dock in Hull. Built off a reinforced concrete raft foundation with an internal  raised concrete floor on metal deck supported by internal blockwork walls forming the duct and cable trenches.  External walls were traditional masonry built with a traditional timber trussesd steel tiled roof. Internally cable trenches were fitted with lightweight GRP flooring panels. Galvanised stairs and concrete landings where constructed externally to provide access to the doors.

     Externally works included the construction of  reinforced concrete transformer pens with 4m high blast walls with palisade fencing completing the enclosures.

    External ducting with cable turning pits, deep surface water drainage, palisade fencing, kerbing macadam, stone and gravel areas completed the works.

  • Grimsby Crematorium - JemBuild
    Grimsby Crematorium Woodland Burial Ground

    The works involve the provision of a Woodland Burial Area within the existing Grimsby crematorium and cemetery grounds. Generally works consist of a new car park, a car park access road along with associated drainage, fencing and landscaping works.

  • ABP - Immingham Lockgates - JemBuild
    Associated British Ports - Immingham Lockgates

    The design and provision of a bespoke storage area for the support of 2no. 150 ton Lock Gates. Works included the excavation and of the existing area, drainage/ducting installation, the removal of an existing sheet piled wall, the installation of heavy duty reinforced concrete foundations and support walls complete with 300mm x 600mm timber sleepers, surfacing works, external lighting tower modifications and the installation of palisade fencing to the full perimeter of the new site.

  • Goole Hoist ABP Cover
    Associated British Ports - No.5 Boat Hoist Refurbishment

    JemBuild are pleased to have been awarded this interesting restoration project in the Port of Goole on this Grade 2 listed Boat Hoist building. Works comprised of an extensive scaffolding design and erection offering access to the 8.5m high platform level to facilitate the removal of existing rotten timber joists, the installation of new timber joists, walkway and handrails. All works carried out utilising traditional joinery methods, including Mortice and Tusk Tenons to the joists and handrails. Works have been monitored by ABP and English Heritage and we are currently awaiting approval to commence with additional cladding and flooring works, which will replace floor joists and floor boards to the 2nd floor within the hoist, some 15m above ground level and also replacement of timber cladding to the inclined façade, approximately 25m high.

    Whilst working on site, we have been awarded significant additional works within the area, including a 70m x 5m heavy duty road to access the boat hoist along with the construction of concrete and block paved access areas.

  • ABP - Goole Transit Sheds - JemBuild-cover
    Associated British Ports, Goole - 18 & 20 Transit Sheds

    Generally the works comprise of the refurbishment of two large transit sheds (Sheds 18 and 20) which included (although not exhaustive) the removal of existing timber cladding (18 Shed), re-cladding works, the installation of new roller shutter doors, cladding improvements, new internal partition walls, drainage works, construction of a concrete dwarf walls to the perimeter of Shed 18, new lighting and general electrical works including extensive external works.

  • Centre4 - Cover Image - JemBuild
    Centre4

    A 26 week project comprising the refurbishment of a former secondary school together with multiple single storey extensions and associated external works to form the new Centre4 Community Centre. 

    Centre4 (formerly Second Avenue Resource Centre) was established in 1995 and exists to support the regeneration of North East Lincolnshire.  It is a vibrant Hub that offers services and activities to the local community as well as incubator space for small businesses and social enterprises. 

    The project achieved a BRREAM very good rating.

  • Healing School - Jembuild
    Healing Science Academy

    A £3.6m Design & Build contract to construct a new three-storey classroom block complete with various associated external works at Healing Science Academy in North East Lincolnshire.

    The project comprises of a 2700m2 new-build element providing eighteen academic classrooms, a large school library, special educational needs facilities and various staff and welfare amenities. External works including a large colonnade extension to the gym building, external shelters, and extensive landscaping were also incorporated as a part of a separate full-plans application.

    A sustainable construction was achieved with the compilation of a dynamic thermal model which successfully proved a naturally ventilated building could be achieved within the scope of the new design by utilising solar control glass, brise soleil and a bespoke dual opening window system throughout the building. Additionally Solar Photovoltaic panels were incorporated within the expansive roof structure providing energy capable of supplying the new build.

    This striking scheme has been well received by the Academy Staff, Board of Governors and more importantly the pupils.